A factory acceptance test, or FAT, is a planned set of checks performed at the manufacturing facility before equipment ships. For switchgear, its purpose is to compare agreed items—such as configuration, wiring, labels, and selected operating functions—with project documents and stated acceptance criteria. A FAT is not one universal test prescribed in the same way for every assembly, and it does not replace field commissioning. Switchgear Builder Virginia can discuss custom-built equipment and a project-specific FAT scope; the proposed checks, documentation, schedule, and applicable ratings must be confirmed for the quoted build.
What a FAT means
A factory acceptance test is a customer- and manufacturer-agreed inspection or test plan carried out on equipment before shipment. The word “acceptance” refers to the project’s defined criteria, not to an automatic certificate that every possible condition has been proven. For a switchgear assembly, the scope might include checking the assembled lineup against approved drawings, confirming component identification and labels, reviewing specified documentation, and demonstrating selected mechanical or electrical functions under controlled factory conditions. Which checks make sense depends on the design, contract, applicable standards, available test arrangements, and the risks the project needs to address. The FAT plan should say what will be examined, how results will be recorded, who may witness the work, and how discrepancies are handled. Without these details, the term alone does not tell a buyer what was actually tested or what the results establish.
Agree on scope first
Before ordering or scheduling a FAT, align the test scope with the equipment submittals, purchase documents, and project acceptance criteria. Identify the exact assembly or sections covered, the drawing revision being used, the inspections and demonstrations requested, and any records required for closeout. Decide whether customer or consultant witnesses are expected, how much notice they need, and whether attendance is in person or handled another agreed way. Clarify how a finding will be documented, who evaluates it, and whether correction and retesting affect shipment timing. These choices matter because a broad phrase such as “full FAT” can mean different things to different parties. A written, equipment-specific plan limits misunderstandings and helps avoid paying for checks that do not address the project’s needs. Final scope, availability, and schedule should be reviewed with the manufacturer and confirmed in the quote or project documents.
Checks depend on the build
A useful FAT reflects the actual switchgear design rather than relying on a generic checklist. A visual review may compare the lineup, installed devices, nameplates, terminal markings, and wiring to the approved documents. Other agreed checks could demonstrate specified interlocks, indications, control circuits, or breaker operation using appropriate factory procedures and test equipment. The team should distinguish a point-to-point or functional demonstration from a test that establishes insulation performance, short-circuit capability, or another specific rating; one does not automatically prove the others. Some checks may require the assembly to be de-energized, isolated, or configured in a defined way, and the safe method belongs in the controlled test plan. Whether a requested test is practical or appropriate depends on the equipment and agreed setup. Ask what each test verifies, what it does not verify, and how the result will be documented before treating it as evidence of project acceptance.
FAT is not commissioning
A FAT takes place at the factory before shipment; field commissioning takes place at the project site and addresses installation-specific readiness and operation. Factory checks cannot establish that equipment arrived undamaged, was installed correctly, has suitable site connections, or works with the actual upstream and downstream system. Commissioning may include site inspections, verification of field wiring and settings, coordination with other equipment, and project-defined functional checks. The precise commissioning scope belongs to the responsible project team and qualified personnel. A successful FAT can reduce uncertainty by finding discrepancies before shipment and by familiarizing stakeholders with the intended configuration, but it is not a substitute for site acceptance or commissioning. Likewise, a commissioning plan does not retroactively define the factory test. Buyers should keep the two scopes separate in schedules, responsibilities, documentation, and acceptance milestones so that neither activity is assumed to cover work assigned to the other.
No universal FAT checklist
A FAT should not be described as a universal, automatically required set of tests unless the governing contract or applicable requirement says so. Requirements can vary with equipment type, project specifications, jurisdiction, and the standards that apply to the particular assembly. For applicable low-voltage switchboards, UL 891 may be relevant to the assembly; it should not be treated as a blanket FAT procedure or as applying to medium- or high-voltage switchgear. Confirm the equipment classification, required markings or approvals, and any specified tests with the project’s engineer and the manufacturer. Switchgear Builder Virginia manufactures new, custom equipment using all-American components, with nationwide shipping and short lead times; actual configuration, schedule, ratings, and any FAT scope remain subject to quotation and verification. Ask for the proposed acceptance criteria and records in writing, and verify that they match the project documents before approving the plan.