Medium-Voltage Switchgear Quote Checklist

New American-built power distribution equipment, engineered around your project.

ENGINEERED FOR POWER
US
Made in the USAAmerican components
✓
Project-specific standardsConfirmed for equipment type
↗
Built to moveLead time quoted by project

BUYING INTENT / MANUFACTURER DIRECT

A useful medium-voltage switchgear quote starts with a clear picture of the electrical system, the required equipment, and the boundaries of the supplier’s scope. Before requesting pricing from Switchgear Builder Virginia, gather the one-line diagram, operating conditions, protection requirements, and project schedule constraints. These details help identify questions early; they do not establish a final design or confirm that a particular configuration is available. Ratings, construction, interfaces, and schedule require review against project documents and confirmation in the quotation.

System Voltage and Class

Document the nominal system voltage and the maximum system voltage the equipment must accommodate. These values are related but not interchangeable, so provide the project’s defined values rather than relying on a shorthand description such as “15 kV class.” Include system frequency, grounding method, and whether the installation is intended for indoor or outdoor use, if known. Note the source and load arrangement, including the number of incoming and outgoing circuits and any tie or sectionalizing positions. Equipment class affects insulation coordination, clearances, component selection, and the available lineup arrangements; it should be confirmed against the actual system requirements. Include environmental conditions such as altitude, ambient temperature, contamination, and enclosure exposure when specified. If any item remains undecided, label it as pending instead of guessing. The quotation should identify assumptions and exceptions so the project team can resolve them before approving a design or comparing proposals.

BIL and Fault Duty

Provide the required basic insulation level (BIL) and the system’s available fault current, along with the required withstand duration when specified. These values help define insulation and short-circuit requirements, but they must be checked against the system study, protection clearing times, and applicable project specifications. Send the source document or study revision so the quoting team can distinguish approved values from preliminary estimates. Identify whether the stated fault duty applies to the bus, incoming devices, feeder devices, or the complete assembly; do not assume one figure answers every equipment question. Ask the supplier to state the proposed ratings and the basis for them in the quote, including any limits or exceptions. If the fault study is incomplete, flag that condition and request a clearly identified preliminary scope rather than treating assumed values as final. Final selection should be verified by qualified project professionals before release for construction.

Devices and Relays

List each required switching and protective device by circuit, including its function, quantity, control voltage, and any specified operating or interface requirements. Identify relay functions and preferred makes or models only when the project documents establish them; otherwise describe the protection functions and request the proposed arrangement for review. Include metering, instrument transformers, sensors, communications, alarms, interlocks, and control power where they are part of the intended scope. Clarify which signals must connect to a plant or building control system, and provide interface documents if available. A detailed device schedule prevents assumptions about what is included, but it does not itself confirm that every requested combination can be furnished. Ask the quote to separate included components from customer-furnished items and options, and to identify information still needed for selection. Relay settings should be coordinated through the project’s protection process, not inferred from a preliminary equipment list or quote description.

Drawings and Interfaces

Attach the latest one-line diagram and mark its revision date. Add control schematics, equipment layouts, cable termination information, bus connections, and interface drawings when available. Identify upstream and downstream equipment, transformer or cable connections, metering points, and any connection constraints that could affect the lineup. State the intended installation location and available access path, along with room dimensions, working clearances, conduit or cable entry preferences, and environmental conditions when confirmed by the project team. Flag existing-system interfaces and planned outages as coordination items; do not assume compatibility from voltage alone. The supplier should review the documents for scope gaps and identify drawing approvals or additional information needed before final engineering. If drawings are preliminary, mark them clearly and explain what may change. Keeping document revisions aligned across the quote, design review, and purchase documents reduces the risk of pricing a configuration that no longer matches the project.

Scope, Schedule, and Review

Describe the requested scope plainly: equipment lineup, devices, relays, accessories, documentation, and any requested field or commissioning support. Ask which items are included, optional, excluded, or dependent on further review. Provide the required ship-to location, requested project milestones, receiving constraints, and the date equipment is needed on site, but treat these as planning inputs rather than a delivery commitment. Switchgear Builder Virginia manufactures new switchgear in the USA using all-American components and offers custom builds with nationwide shipping; configuration, capability, and schedule remain subject to quote and verification. Before comparing proposals, check that each uses the same voltage, insulation, fault-duty, device, and documentation basis. Resolve deviations in writing and have the responsible engineering team review ratings, protection coordination, and interfaces. An accepted quote is not a substitute for final approved drawings or project-specific technical review.

Related project guides

START A CONVERSATION

Let’s build the right solution.

Tell us what you’re building, replacing or upgrading. Share the information you have now; project details and availability can be confirmed together.